Contract No. HKI/2024/07 - Hydraulic Improvement of Stormwater Drainage System (SMH7010840) in Whitty Street Qurrn's Road West
2024 - 2025
Before
After
Project Overview
A targeted hydraulic improvement was carried out on a 600 mm diameter stormwater drain by replacing a short defective section using a fully trenchless coring method. All works were executed from the existing manholes, eliminating the need for open‑trench excavation at this busy urban junction.
Client
Drainage Services Department
Contract No.
HKI/2024/07 – Rehabilitation and Replacement at Hong Kong Island (Central and Western) (Package 4)
Location
Whitty Street / Queen’s Road West, Hong Kong
Pipe Diameter
600 mm
Length
2 m
Completion
August 2025
Key Technique – Trenchless Coring & Pipe Installation
Pre‑Works Survey – CCTV inspection and underground utility survey confirmed pipe condition and adjacent services.
Guide Wire Installation – A steel wire was propelled from the downstream manhole to the upstream manhole to maintain precise alignment and invert level.
Coring Machine Jacking – A coring machine (CABEL CSN‑6A) jacked steel coring pipes along the guide wire to clear any obstructions, protect the host pipe, and create a safe working channel.
New Pipe Installation – Replacement uPVC pipe sections (each 600 mm long) were jacked into position from the downstream manhole, connected via flexible spigot‑and‑socket joints with elastomeric seals, forming a smooth, durable new conduit.
Manhole Reinstatement – All coring equipment was removed and anchor points were sealed with high‑strength concrete grout.
Final Verification – Post‑installation CCTV survey confirmed correct alignment and structural integrity.
Highlights
-
Zero surface excavation – works accessed solely through two manholes
-
No traffic disruption on Whitty Street or Queen’s Road West
-
Rapid completion within a single shift, including reinstatement
-
Enhanced hydraulic capacity restored with seamless, joint‑minimised pipe structur